Insulation resistance

Updated 2026-10-13

Data records

  • Insulation Resistance is specified for low-voltage ground-fault protection systems in acceptance testing at clause 7.14.B.2 of ANSI/NETA ATS-2025. Value: low-voltage ground-fault protection systems. Source: ANSI/NETA ATS-2025, clause 7.14.B.2. Verified 2026-10-13. Record tests.insulation-resistance.equipment.relay.acceptance
  • Insulation Resistance is specified for low-voltage ground-fault protection systems in maintenance testing at clause 7.14.B of ANSI/NETA MTS-2023. Value: low-voltage ground-fault protection systems. Source: ANSI/NETA MTS-2023, clause 7.14.B. Verified 2026-10-13. Record tests.insulation-resistance.equipment.relay.maintenance

Sources

  • ANSI/NETA ATS-2025, Acceptance Testing Specifications for Electrical Power Equipment and Systems, 2025 edition, NETA. Cited: clause 7.14.B.2. Held as: Purchased single-user copy. Publisher page
  • ANSI/NETA MTS-2023, Maintenance Testing Specifications for Electrical Power Equipment and Systems, 2023 edition, NETA. Cited: clause 7.14.B. Held as: Purchased single-user copy. Publisher page

Obtaining the documents

Changelog (2 entries)
DateRevisionChange
2026-10-13created (tests.insulation-resistance.equipment.relay.acceptance)
2026-10-13created (tests.insulation-resistance.equipment.relay.maintenance)

Cite this page

Cite the governing standard for the fact itself; cite this page as the finding aid.

"Insulation resistance." Protective Relay Reference. 2026-10-13. https://www.protectiverelayreference.com/tests/insulation-resistance/.