Clause 8.2.3 of IEEE 1547.1-2020 makes verification of the DER's voltage and frequency tripping functions and of its cease-to-energize behavior mandatory at commissioning, and it allows signal injection where actual adjustment of the voltage and frequency is impractical.

ProvenanceIEEE 1547.1-2020 supports data record tests.protective-relay-element-tests.ieee1547-1.commissioning-verification, which is cited on the entry Protective Relay Element Tests.SOURCEIEEE 1547.1-2020IEEE 1547.1-2020Licensed standard, clause 8.2.3DATA RECORDtests.protective-relay-element-tests.ieee1547-1.commissioning-verificationtests.protective-relay-e..Verified 2026-10-24ENTRYProtective Relay Element TestsProtective Relay Element..No revisions
Provenance. Where this record comes from and where it is used: the cited source, the record itself and the entry that cites it.
Provenance: the chain from source to entry.
StepItemDetail
SourceIEEE 1547.1-2020Licensed standard, clause 8.2.3
Data recordtests.protective-relay-element-tests.ieee1547-1.commissioning-verificationVerified 2026-10-24
EntryProtective Relay Element TestsNo revisions
Subject
Protective Relay Element Tests (Test methods)
Kind
Method fact
Source
IEEE 1547.1-2020, clause 8.2.3, Conformance Test Procedures for Equipment Interconnecting Distributed Energy Resources, IEEE.

History

Every recorded change to this data record, oldest first.
DateChange
2026-10-24created
2026-10-24revised
2026-10-24review_status unreviewed -> software_reviewed

Cite this page

Cite the governing standard for the fact itself; cite this page as the finding aid.

"Data record tests.protective-relay-element-tests.ieee1547-1.commissioning-verification." Protective Relay Reference. 2026-10-24. https://www.protectiverelayreference.com/data/tests.protective-relay-element-tests.ieee1547-1.commissioning-verification/.